SAP PS: from the first WBS element to the final asset

Project System, explained for users and for consultants from other modules.

Read as

Overview

What PS is, if you have never worked with it

SAP PS, the Project System, is the part of SAP that runs work with a start and an end: building a production line, rolling out a system, developing a product, delivering a plant to a customer. SAP’s own description covers anything from building a factory to organizing a trade fair. PS breaks the work into a work breakdown structure (WBS) that carries the money and, where the work must be scheduled, staffed or bought, a network of activities. Because it is integrated with the rest of SAP, the project is planned, executed and accounted for inside the normal business processes.

This page is for the people who work around PS without being PS consultants: project managers, controllers and key users, and FI, CO, MM or SD consultants who keep meeting WBS elements. It follows one capital project from the first structure to the final fixed asset, lets you test the budget check and the settlement yourself, and lists the transactions worth knowing.

Runs on
  • SAP ECC 6
  • SAP S/4HANA
  • SAP S/4HANA Cloud Private Edition
Main transactionsCJ20NCJI3CJ88

Use the User | Consultant switch at the top of the page to show or hide the technical layer: Customizing transactions, tables and the settings behind each step.

  • What and when: two structures

    The WBS says what is done and who is responsible, and it carries plans, budgets and actual costs. The network says how and when: activities with durations and relationships that schedule the work, plan internal hours and, for external activities, create purchase requisitions on their own.

    Source: SAP Learning, creating a WBS
  • Plan, budget, check

    The plan is an estimate; the budget is the money that was approved. Once a WBS element has a budget, availability control checks every business transaction that assigns cost to it, such as a purchase order, and warns or blocks before the money is gone.

    Source: SAP Learning, budgeting functions
  • Every project is settled

    A WBS element only collects. At period end, settlement moves its costs to the real receiver: an asset under construction and then fixed assets for a capital project, cost centers for an internal one, profitability for a customer project. That is why FI and CO meet PS every close.

    Source: SAP Learning, period-end closing for projects

Three kinds of project

Capital projectOverhead projectCustomer project
ExampleA new canning lineA system rollout, an R&D studyA line built for a customer
RevenueNoneNoneOn the billing element, from the sales order
Settled toAsset under construction, then fixed assetsCost centersProfitability (Margin Analysis)
Key settingInvestment profileSettlement rule to cost centersResults analysis key or revenue recognition key
Period-end extraInterest, if capitalizedOverheadResults analysis or event-based revenue recognition

Sources: SAP Learning, executing a settlement and performing results analysis; SAP blog, results analysis concept; SAP Community, settlement of capital and cost projects.

This page uses one example

P-27001, a new canning line in a brewery

A capital project with four WBS elements, engineering, equipment, installation and operator training, and a network that schedules the installation. It appears in the process, in the budget check you can try and in the settlement to fixed assets. Numbers are examples only.

Who PS talks to

A project touches almost every module, which is why a “project problem” so often ends up on a CO, FI-AA or MM desk.

  • COPrices, overhead, settlementActivity prices value confirmed hours; overhead, interest and settlement run in Controlling at period end.
  • FI-AAAssets under constructionCapital projects build an AuC, created at release by the investment profile, and capitalize it into fixed assets at the end.
  • IMInvestment programsInvestment Management plans capital budgets above the projects and distributes them down to their WBS elements.
  • MMPurchasing and project stockRequisitions from activities and components, orders with account assignment P, Q or N, goods issues 221 and 281.
  • SDCustomer projectsSales orders assigned to billing elements, billing plans and resource-related billing.
  • CATSTime sheetsHours entered in CAT2 reach the network after the CAT5 transfer and post as activity allocations.

Building blocks

What a project is made of

Most “I can’t post to the project” calls start with one of these objects. Pick one to see what it holds, why Controlling cares and where it is maintained.

Project object

Templates copy the whole structure into a new project in one step: a standard WBS (CJ91) and a standard network (CN01).

The frame

Project definition

The frame around everything: number, description, dates and the project profile that sets the rules. The organization it carries, controlling area, company code and plant, is defaulted to the WBS elements below. You cannot post costs to it.

Example: P-27001 New canning line, with the project profile for capital projects

Why CO cares

It is not an account assignment object, so it never appears on a journal entry; reports add up the WBS elements below it.

Maintain inCJ20NCJ06

Consultant toolsOPSAOPSJ

Customizing for each object is in the Consultant view.

Sources: SAP Learning, creating operative WBS and customizing WBS.

The cost object

WBS element

A piece of the work in a hierarchy. Three operative indicators decide what it can do: planning element, so costs can be planned on it; account assignment element, so actual costs and commitments can post and orders, networks and purchase orders can be assigned; billing element, so revenues can be planned and billed.

Example: P-27001.2 Equipment: planning element and account assignment element

Why CO cares

Each WBS element is a CO object with its own plan, budget, actuals, commitments and settlement rule. Company code, profit center and the responsible cost center sit in its master data.

Maintain inCJ20NCJ12

Consultant toolsOPSACNMASS

Customizing for each object is in the Consultant view.

Sources: SAP Help, operative indicators; SAP Learning, creating a WBS; SAPSTACK, table PRPS.

How and when

Network

The schedule of the work: a network header with activities linked by relationships, scheduled forward or backward, much like a project plan. Technically it is an order: its header sits in the same tables as production orders, with its own network type.

Example: Network 4000123, assigned to P-27001.3 Installation

Why CO cares

Costs sit on the network header or, more often, on each activity, and are settled to the WBS element the network belongs to.

Maintain inCJ20NCN22

Consultant toolsOPSCOPUU

Customizing for each object is in the Consultant view.

Sources: SAP Learning, scheduling networks; SAP KBA 2483450; Tutorialspoint, network type; SAP Community, network settlement.

Checkpoints

Milestone

A point that matters: an approval, a delivery, the end of a phase. Milestones can set the dates of a milestone billing plan, measure progress with the milestone technique and feed milestone trend analysis, which shows whether the project is slipping.

Example: M-03 Line accepted by the brewery

Why CO cares

In customer projects a milestone can release the next invoice of the billing plan, which moves revenue on the billing element.

Maintain inCJ20NCNMT

Consultant toolsCN11

Customizing for each object is in the Consultant view.

Sources: SAP Learning, progress analysis and milestone trend analysis; SAP Help, standard structures.

Revenue

Billing plan

On a billing element or on the sales order assigned to it: the dates and amounts to invoice, by milestone or by period. Resource-related billing, DP91, instead builds the invoice from the costs actually incurred.

Example: 30% at order, 50% at delivery, 20% at acceptance

Why CO cares

Billing posts revenue to the billing element; results analysis or event-based revenue recognition then matches revenue and cost by period.

Maintain inVA02DP91

Sources: SAP Help, billing plan and resource-related billing; SAP Learning, revenue planning.

The work itself

Activity

A task in the network. Internal activities plan work on a work center with an activity type; external ones buy the task from a vendor; general cost activities plan any other cost, such as travel; service activities buy services. The control key decides which, and whether the activity is costed, scheduled and confirmed.

Example: 0010 Remove old filler, internal, 120 h; 0020 Install new filler, external

Why CO cares

Internal activities are valued with the cost center’s activity price: planned cost is hours times rate, and each confirmation posts an activity allocation from the cost center.

Maintain inCN22CN25

Consultant toolsOPSUKP26

Customizing for each object is in the Consultant view.

Sources: SAP Help, control keys; SAP Learning, cost planning of internal and external activities.

Materials

Material component

Materials planned on an activity. Stock items create reservations and are issued from stock; non-stock items create purchase requisitions. With project stock, quantities and values are kept per WBS element until they are used.

Example: Conveyor belt kit, non-stock, bought for activity 0020

Why CO cares

The account assignment category and whether project stock is valuated decide when the cost hits the project: at the goods receipt or at the goods issue.

Maintain inCJ20NMIGO

Consultant toolsOPTT

Customizing for each object is in the Consultant view.

Sources: SAP Learning, processing material requirements; SAP Community, account assignment Q and P.

Where the money goes

Settlement rule

Distribution rules on the WBS element or network that say where its costs go: a cost center, an asset under construction, a fixed asset, a profitability segment, another WBS element. Capital projects get the AuC rule automatically at the first settlement; the rule to the final assets is entered when they exist.

Example: P-27001.2 to AuC 4000-0012, later to the Filler (60%) and the Conveyor (40%)

Why CO cares

Settlement credits the project and debits the receiver, so it is the posting that finally turns project cost into an asset, an expense or a margin.

Maintain inCJ20NCJ88

Consultant toolsOITA

Customizing for each object is in the Consultant view.

Sources: SAP Learning, executing a settlement; SAP Community, settlement to AuC and final asset.

The PS process

Follow one project from the structure to the fixed asset

Nine steps of a project in SAP PS. The first five only plan and approve; from the first purchase on, steps post. Step 8 is for customer projects only. Pick a step to see what happens, where you see it, what it posts in the books and, in the Consultant view, what sits under the hood.

Process step

Step 1 of 9 · What happens

The project is structured

The project starts as a structure: a project definition, WBS elements in a hierarchy and, where the work must be scheduled, staffed or bought, networks with activities. Most companies copy a template, a standard WBS or a standard network, rather than starting from zero. Everything starts in status CRTD, created.

Who: Project manager, PS key user

Where you see it

The Project Builder, CJ20N, for everything; templates in CJ91 and CN01; the Project Planning Board, CJ2B, as a Gantt chart.

  • CJ20N
  • CJ91
  • CN01

Under the hood

The project profile (OPSA) defaults the organization, the profiles and the WBS behavior. The coding mask (OPSJ) formats the numbers and can derive the hierarchy from them; you can add to a mask later but not take anything away. Networks get a network type (OPSC) and a network profile (OPUU).

  • OPSA
  • OPSJ
  • OPSC
  • OPUU

Customizing, tables and the settings behind this step are in the Consultant view.

No postingIn the books: Nothing posts. A structure is master data.

Sources: SAP Learning, customizing WBS and creating operative WBS; SAP Help, maintaining standard structures.

Step 2 of 9 · What happens

The dates are scheduled

WBS elements get basic dates, and networks schedule their activities from durations and relationships, forward from a start date or backward from a finish date. Several networks linked to each other can be scheduled together.

Who: Project planner

Where you see it

Scheduling in the Project Builder or the Project Planning Board (CJ2B); overall network scheduling in CN24N; in SAP S/4HANA, the Project Schedule app shows the same as a modern Gantt chart.

  • CJ2B
  • CN24N

Under the hood

The project profile carries the WBS scheduling settings and the planning board profile. In SAP S/4HANA the planning board is modernized by the Project Schedule app (2021) and the network graphic by the Project Network Graph app (2020 FPS1).

  • OPSA
  • CJ2B

Customizing, tables and the settings behind this step are in the Consultant view.

No postingIn the books: Nothing posts. Dates drive capacity and purchasing later, not the books.

Sources: SAP Learning, scheduling networks and checking the project schedule; SAP PRESS, project planning with SAP S/4HANA; SAP blog, compatibility scope for EPPM.

Step 3 of 9 · What happens

The costs are planned

Costs are planned top-down on the WBS as overall values, in detail by cost element, with Easy Cost Planning, or bottom-up from the network: internal activities as hours times the activity price, external activities from the purchasing price, general cost activities as an amount. A plan is an estimate; nothing is approved yet.

Who: Project controller, planner

Where you see it

Overall planning in CJ40, detail planning in CJR2, Easy Cost Planning in CJ9ECP or from the Project Builder; network costs appear on the activities.

  • CJ40
  • CJR2
  • CJ9ECP

Under the hood

The planning profile (OPSB) controls manual planning on WBS elements; the network profile defaults cost elements and control keys. In SAP S/4HANA, CJ40 and CJR2 still work but write the classic tables, not ACDOCP; Easy Cost Planning and network costing write to ACDOCP from release 2022, and SAP Analytics Cloud is the strategic planning tool.

  • OPSB
  • OPUU
  • ACDOCP

Customizing, tables and the settings behind this step are in the Consultant view.

No postingIn the books: No journal entry. Plans are CO plan values, the yardstick for every plan-versus-actual report.

Sources: SAP Learning, configuration for cost planning and cost planning of internal and external activities; SAP blog, controlling in SAP S/4HANA part 2; SAP blog, compatibility scope for EPPM.

Step 4 of 9 · What happens

The budget is approved

The budget is the money that was approved, often proposed from the plan. It is entered as an original budget, overall or by year, and then changed with supplements, returns and transfers rather than by overwriting. The WBS element gets status BUDG and, if the budget profile says so, availability control switches on.

Who: Project controller, management

Where you see it

Original budget in CJ30, display in CJ31; supplements in CJ36 and CJ37, returns in CJ35 and CJ38, transfers in CJ34; budget line items in CJI8.

  • CJ30
  • CJ37
  • CJ34

Under the hood

The budget profile (OPS9) sets overall or annual budgeting and availability control: its activation type, for example automatic when the budget is allocated, and the tolerance limits per activity group. Status AVAC shows availability control is active; CJBV activates it for existing projects and CJBW deactivates it.

  • OPS9
  • CJBV
  • CJBW

Customizing, tables and the settings behind this step are in the Consultant view.

No postingIn the books: Nothing posts in the ledger. Budget lives in CO tables, BPGE for overall values and BPJA for annual ones, and is checked, not booked.

Sources: SAP Learning, budgeting functions; SAP Community, SAP PS budget management; SAP blog, configuring budget availability control; SAP Help, the budgeted status.

Step 5 of 9 · What happens

The project is released

Release, status REL, says the work can start: actual costs can now post. With an investment profile on the WBS element, Asset Accounting gets an asset under construction automatically at release. Some companies also release the budget in steps with CJ32, so not all approved money can be spent at once.

Who: Project manager

Where you see it

Release in the Project Builder; budget release in CJ32; the AuC can be reached from the WBS element and seen in the Asset Explorer, AW01N.

  • CJ20N
  • CJ32
  • AW01N

Under the hood

System statuses decide what is allowed: in CRTD you can plan, budget and even create purchase requisitions and orders, which are commitments, but not post actual costs. The investment profile (OITA) controls the automatic AuC and its asset class.

  • OITA
  • BS23

Customizing, tables and the settings behind this step are in the Consultant view.

No postingIn the books: No journal entry yet, but the project is open for actual costs, and the AuC exists in Asset Accounting with no value.

Sources: SAP Learning, the status of a project and executing a settlement; SAP blog, release and budgeting; SAP Community, SAP PS budget management.

Step 6 of 9 · What happens

Materials and services are bought

External activities and non-stock components create purchase requisitions on their own; buyers turn them into purchase orders assigned to the WBS element (account assignment P) or to the network (N). Each one becomes a commitment and is checked against the budget the moment it is saved. Stock materials go out with goods issue 221 to a WBS element or 281 to a network.

Who: Buyer, warehouse

Where you see it

Purchase orders in ME21N; goods receipt and goods issue in MIGO; open commitments in CJI5.

  • ME21N
  • MIGO
  • CJI5

Under the hood

Account assignment Q works with project stock: quantities and values are kept per WBS element until the goods issue. Whether the cost lands at the goods receipt (P, like a non-stock item) or at the goods issue (Q, from valuated project stock) changes when it shows on the project.

  • P
  • Q
  • N
  • 221
  • 281

Customizing, tables and the settings behind this step are in the Consultant view.

FI postingIn the books: The goods receipt of a non-stock item, or the goods issue from stock, debits the WBS element or network; the invoice then clears the GR/IR account.

Sources: SAP Learning, processing material requirements; SAP Help, external processing data and movement types; SAP Community, account assignment categories.

Step 7 of 9 · What happens

People confirm their time

Internal work is confirmed against network activities: hours worked, remaining work and whether the activity is finished. Many companies collect the hours in the Cross-Application Time Sheet (CATS) and transfer them to the network in a batch.

Who: Project team, supervisor

Where you see it

Individual confirmation in CN25, collective in CN27, cancellation in CN29; time sheet in CAT2, transfer to PS with CAT5.

  • CN25
  • CN27
  • CAT2
  • CAT5

Under the hood

The activity’s work center, activity type and control key decide the valuation; the price comes from the cost center’s activity price. Records that CAT5 cannot post go to an error pool for post-processing, so a time sheet reaches the project only after the transfer.

  • CAT5
  • KP26

Customizing, tables and the settings behind this step are in the Consultant view.

FI postingIn the books: Confirmed hours times the activity price debit the network or WBS element and credit the cost center: an activity allocation, recorded in the universal journal in SAP S/4HANA.

Sources: SAP Learning, activity confirmation and CATS; SAP KBA 2665885; SAP Community, CATS transfer and the error pool.

Step 8 of 9 · What happens

Customer projects bill and recognize revenue

Only for customer projects. A sales order assigned to the billing element carries the billing plan, by milestone or by period, or resource-related billing builds the invoice from the costs actually incurred. Revenue lands on the billing element. Capital and internal projects skip this step.

Who: Billing clerk, project controller

Where you see it

Billing plan on the sales order, VA02; resource-related billing request in DP91; revenue and margin in the project reports.

  • VA02
  • DP91

Under the hood

In SAP ECC, results analysis (KKA2 for one WBS element, KKAJ for many) calculates the revenue to recognize, work in process and reserves at period end. In SAP S/4HANA, event-based revenue recognition posts recognized revenue at each cost or billing event; results analysis is not supported with Universal Parallel Accounting.

  • KKA2
  • KKAJ
  • EBRR

Customizing, tables and the settings behind this step are in the Consultant view.

FI postingIn the books: The invoice posts revenue and a receivable with the billing element as account assignment; recognized revenue follows at period end with results analysis, or in real time with event-based revenue recognition.

Sources: SAP Help, billing plan and resource-related billing; SAP Learning, performing results analysis; SAPinsider, real-time revenue recognition; SAP blog, EBRR with Universal Parallel Accounting.

Step 9 of 9 · What happens

Period end, settlement and close

Every month overhead and, if configured, interest are calculated, then settlement empties the WBS elements: capital projects to the asset under construction, internal ones to cost centers, customer ones to profitability. When the work is done the project goes to TECO, a full settlement moves the AuC to the final fixed assets, and CLSD closes it.

Who: Project controller, asset accountant

Where you see it

Overhead in CJ44 or CJ45, interest in CJZ2 or CJZ1, settlement in CJ88 or CJ8G; asset values in AW01N.

  • CJ45
  • CJ88
  • CJ8G

Under the hood

Periodic settlement to the AuC uses the rule the investment profile generates. The final settlement needs the final assets created and entered in the settlement rule, and runs as a full settlement. CJIC settles single AuC line items to final assets.

  • OITA
  • CJIC
  • AW01N

Customizing, tables and the settings behind this step are in the Consultant view.

FI postingIn the books: Settlement credits the WBS element and debits the receiver: the AuC, a balance sheet account, or a cost center, or profitability. The full settlement credits the AuC and debits the fixed assets.

Sources: SAP Help, project period-end closing and final settlement for a project; SAP Learning, executing a settlement and full settlement of investment WBS elements; SAP Community, settlement to AuC and final asset.

The four statuses FI and CO watch

A WBS element carries many statuses, but month-end turns on four. They decide whether it can take actual costs, whether new purchasing is still possible and whether anything can post at all.

  • CRTD · CreatedPlan, yes; post, noStructure, dates, costs and budget can be planned, and purchase requisitions and orders can already be created as commitments. Actual costs are refused with message BS013, system status CRTD is active.
  • REL · ReleasedCosts can arriveActual costs and revenues post. With an investment profile, the asset under construction is created now. A WBS element added under a released one is released too.
  • TECO · Technically completedDone, but invoices still comeThe work is finished but costs are still expected: goods receipts and invoices for existing orders post, new purchasing documents normally don’t. It can be revoked back to REL.
  • CLSD · ClosedNothing more postsNo more actual costs, no changes to the hierarchy, and the asset under construction assigned to the element is deactivated. It can be revoked back to TECO if something was forgotten.

Sources: SAP Help, system statuses in work breakdown structures; SAP Learning, displaying the status of a project; SAP KBA 2877967; SAP Community, postings in CRTD, TECO and CLSD.

Try it: budget

Will my purchase order get through?

Availability control is the PS feature users meet without knowing its name, usually as an error when they save a purchase order. It does not compare the order with the invoices so far. It adds the order to everything already assigned to the WBS element, actual costs plus open commitments, and compares that with the budget. Change the inputs and watch the message change.

WBS P-27001.2, Equipment

Example: budget 1,000,000, 800,000 already assigned and a purchase order of 150,000, with 90% warning and 100% error limits.

USD, examples only. Tolerance limits are set per budget profile and activity group in Customizing, under Project System › Costs › Budget › Define tolerance limits.

What availability control sees

  • Already assigned
  • This document
  • 90% warning
  • 100% budget
  • Error above 100%
Budget
1,000,000
Assigned before
800,000
This document
150,000
Assigned after
950,000
Available after
50,000
Usage
95.0%

BP613Warning

Item 010 WBS element P-27001.2 budget almost exhausted

A warning only: the purchase order can be saved. Usage is now 95.0%, past the 90% warning limit.

What you can do

Save, and tell the project controller: the next document may be blocked. Ask in time for a supplement or a transfer.

  • CJ37
  • CJ34

Where you see the numbers

CJ31 shows the budget of each WBS element; report S_ALR_87013558 lists budget, actual, commitment, remaining plan and assigned side by side; CJI5 lists the open commitments that count as assigned.

  • CJ31
  • S_ALR_87013558
  • CJI5

The number in the message

BP613 says the budget is almost exhausted; BP603 says it is exceeded. Whether either one is a warning or an error that stops the document is decided by the tolerance limits, not by the message number.

Simplified: one WBS element, overall values, one activity group. A real budget profile can check annual values or the released budget instead of the overall budget, and can send a warning with a mail to the person responsible. Sources: SAP Help, availability control actions and tolerance limits; SAP blog, configuring budget availability control; SAP Community, BP613 and BP603 thresholds and postings without tolerance limits; SAP KBAs 3683535 and 3730654.

Try it: settlement

From the WBS element to the fixed asset

This is the part FI-AA and CO people ask about most: how money spent on a project ends up as fixed assets on the balance sheet. Pick how the investment profile settles and where the operator training goes, then walk the project month by month and watch the WBS elements, the asset under construction and the final assets fill and empty.

Example: periodic settlement to the AuC, operator training expensed to its cost center, month 1.

Month 1. The project is released, so the AuC exists. An engineering firm invoices the line design.

Posted to the WBS this month

120,000

All of it is settled at month end, so nothing stays on the WBS elements.

Asset under construction

120,000

AuC 4000-0012, created at release. Balance at month end.

Fixed assets

0

Nothing yet: the final assets are capitalized at the end.

Expense on cost center 4300

0

Operator training, when the rule sends it there.

MIRO

Engineering services

AccountDebitCredit
Engineering servicescost on P-27001.1120,000
Vendoraccounts payable120,000

Account assignment P on the purchase order sends the invoice to the WBS element.

CJ88 · periodic settlement

Month-end settlement

AccountDebitCredit
Asset under constructionAuC 4000-0012120,000
Settlement creditWBS elements120,000

The first settlement creates the rule to the AuC from the investment profile. The WBS elements are emptied; Asset Accounting shows the amount as AuC acquisitions.

Simplified: one AuC for the whole project, no overhead, interest, down payments or taxes, hours at 100.00 per hour. Event-based settlement is the SAP S/4HANA option for small investment projects; periodic summary settlement is the classic one. Which G/L accounts the postings reach depends on your account determination. Sources: SAP Learning, executing a settlement, the asset under construction process, periodic and full settlement of investment WBS elements and small investment projects; SAP Help, periodic and final settlement for a project; SAP Community, creating the final asset before the full settlement.

Quick test

Why can’t I post to my WBS element?

Eight calls every PS support team knows by heart. Guess the cause first, then open the card to see it, the fix and who acts.

  • Status
  • Master data
  • Budget
  • Settlement
  • “System status CRTD is active”Show the answer
    Status

    The WBS element is still created, not released. Plans, budgets and even purchase orders are allowed in CRTD, but actual postings are refused with message BS013. Release the element, or the project, in the Project Builder.

    Who acts: Project manager

  • The WBS element is refused as account assignmentShow the answer
    Master data

    Only WBS elements flagged as account assignment elements take actual costs, commitments and assigned orders. Post to an element below that has the indicator, or set it if the design allows.

    Who acts: PS key user

  • “Budget exceeded” on a purchase orderShow the answer
    Budget

    Availability control added the order to the actual costs and open commitments and went past the error limit (message BP603). Get a supplement or a transfer, reduce the order, or close old commitments.

    Who acts: Project controller

  • The element is lockedShow the answer
    Status

    A lock status such as LKD or AALK (account assignment locked) is set, so FI postings and new purchasing are refused with BS013. Remove the lock in the Project Builder. LKD does not stop MRP from creating proposals.

    Who acts: Project manager

  • TECO, and the new purchase order is refusedShow the answer
    Status

    Technically completed means the work is done: invoices and goods receipts for existing orders still post, new purchasing documents normally don’t. Revoke TECO if the work really continues.

    Who acts: Project manager

  • CLSD, and nothing posts at allShow the answer
    Status

    Closed blocks actual postings and deactivates the AuC. Revoke CLSD back to TECO, post what was forgotten, settle and close again.

    Who acts: Project controller

  • Settlement says CRTD is active, but the screen shows PRELShow the answer
    Settlement

    PREL, partially released, appears when an element below is released, but CRTD can still be active on the element itself. Release the elements that carry costs before running CJ88.

    Who acts: Project controller

  • “Asset under construction not completely credited”Show the answer
    Settlement

    A full settlement must move everything on the AuC to final assets. Create the final assets, enter them in the settlement rule so the shares add up to 100%, and run CJ88 as a full settlement.

    Who acts: Asset accountant, project controller

Sources: SAP Help, system statuses and operative indicators; SAP KBAs 2877967, 3048425, 2797833 and 3420256; SAP Community, BP603, TECO, CLSD, PREL and AuC settlement threads.

Speak PS

The short codes PS people use

PS people talk in codes: “the element is REL with AVAC, it’s an Acct element, buy it with Q, issue with 221 and settle FUL to the asset”. These are the standard ones you will hear in meetings and see on every screen. Your company may add its own.

Code family

Read the status line left to right. CRTD, PREL, REL, TECO, CLSD is the life cycle; the others are flags beside it. The status button in the Project Builder shows which business transactions each one allows.

Three ticks decide what a WBS element can do. They sit on the basic data of every WBS element, as fields PLAKZ, BELKZ and FAKKZ in table PRPS. Whether they can still be changed depends on the status.

The control key tells an activity what it is. Standard network keys start with PS; your company may have its own. The control key cannot be changed for general cost activities or services, nor once the activity is released.

A budget is changed, not overwritten. After the original budget, changes go in as supplements, returns and transfers; a user status can even freeze the original budget while still allowing them, so the budget history stays readable.

How purchasing finds the project. The account assignment category on the requisition or order and the movement type on the goods issue tell SAP where the cost goes.

Who receives the money. The settlement profile limits which receivers and settlement types a WBS element may use; the investment profile adds the AuC.

  • CRTDCreatedPlan and budget, but no actual postings.
  • PRELPartially releasedAn element below is released; the element itself may still be CRTD.
  • RELReleasedActual costs and revenues can post.
  • TECOTechnically completedWork done; costs from existing orders can still arrive.
  • CLSDClosedNo more actual postings; the AuC is deactivated.
  • BUDGBudgetedA budget was allocated; the status stays even if the budget is returned.
  • AVACAvailability control activePostings and commitments are checked against the budget.
  • AUCAsset under constructionAn AuC exists for the element, created by the investment profile.
  • LKDLockedTransactions such as FI postings are refused; MRP still plans.
  • AALKAccount assignment lockedThe element refuses new account assignments.
  • FNBLFinal billingNo more billing; costs, such as warranty, can still post.
  • DLFLDeletion flagAll business transactions are blocked.
  • PEPlanning elementCosts can be planned on it.
  • AcctAccount assignment elementActual costs, commitments and assigned orders, networks and purchase orders.
  • BillBilling elementRevenues can be planned and billed; sales orders are assigned to it.
  • SumProject summarizationThe element is included in project summarization reporting.
  • PS01Internal processingWork on a work center, confirmed and costed with the activity price.
  • PS02External processingBought from a vendor through a purchase requisition.
  • PS03General costsAn amount on a cost element, such as travel or freight.
  • SRVServiceServices bought with a service specification and entry sheet.
  • ELEMActivity elementA part of an activity, of any of the same kinds.
  • MSMilestoneA checkpoint on an activity or a WBS element.
  • CJ30Original budgetThe first approved budget, overall or by year.
  • CJ32ReleaseThe part of the budget that may be spent now.
  • CJ36Supplement to projectMore money from outside, for one or more projects.
  • CJ37Supplement in projectMore money inside one project.
  • CJ35Return from projectMoney given back out of the project.
  • CJ38Return in projectMoney given back inside one project.
  • CJ34TransferFrom one WBS element or project to another.
  • CJCOCarry forwardUnused annual budget moved to the next year.
  • PProjectCost straight to the WBS element, like a non-stock item.
  • QProject make-to-orderProject stock, quantities and values kept per WBS element.
  • NNetworkCost to a network activity.
  • 221Goods issue for a projectStock consumed by a WBS element.
  • 281Goods issue for a networkStock consumed by a network activity.
  • CJ88Periodic settlementEach month, from the WBS element to the AuC or to cost centers.
  • FULFull settlementAt the end, everything on the AuC to the final assets.
  • PREPreliminary settlementDistribution rules applied before the settlement to the AuC.
  • AuCAsset under constructionThe receiver while a capital project runs.
  • CJICLine-item settlementSingle AuC line items assigned to final assets.
  • S/4Event-based settlementSmall investment projects post straight to the AuC.

Sources: SAP Help, system statuses in WBS and the budgeted status; SAP KBAs 3048425 and 2797833; SAP Community, PREL and CRTD.

Sources: SAP Help, operative indicators; SAP Learning, creating a WBS and customizing WBS; SAPSTACK, table PRPS.

Sources: SAP Help, control keys and external processing data; SAP Community, network activity categories; Tutorialspoint, activity control key.

Sources: SAP Help, budget updates; SAP Community, SAP PS budget management and CJ35 to CJ38; ERPlingo, CJ37.

Sources: SAP Help, movement types and account assignment; SAP Learning, processing material requirements; SAP Community, account assignment categories P, Q and N.

Sources: SAP Learning, executing a settlement and small investment projects; SAP Help, final settlement for a project; SAP Community, PRE and FUL settlement and CJIC.

Network = order

Behind the Gantt chart, a network is an order from the same family as production and maintenance orders. Its header sits in AUFK and AFKO with order category 20, its activities in AFVC and AFVV, its components in RESB. PP consultants already know the tables; CO consultants already know how orders settle. Source: SAP KBA 2483450, order category 20

Reference

The PS transactions people actually use

PS transactions follow a pattern: CJ for projects, WBS elements, budgets and settlement, CN for networks, confirmations and the overviews, CJI for line items and OP for most PS Customizing. Start here shows the ones worth bookmarking; FI/CO bridge collects what controllers and asset accountants run; the last column says what changed in SAP S/4HANA. Type a code or a word to search all of them.

Show

Code or appForWhat it doesWho opens itECC / S/4HANA
CJ20NUserProject Builder: create, change and display project definitions, WBS elements, networks, activities and milestones on one screen.Project manager, everyoneECC + S/4HANA
CJ2BUserProject Planning Board: the project as an interactive Gantt chart; CJ27 creates a project there and CJ2C displays one.Project plannerECC + S/4HANA
PSHLP20UserProject Editor, another way to maintain the structure and dates.Project plannerECC + S/4HANA
CJ06UserCreate a project definition; CJ07 changes and CJ08 displays it.Project managerECC + S/4HANA
CJ01UserCreate a work breakdown structure; CJ02 changes and CJ03 displays it.Project managerECC + S/4HANA
CJ11UserCreate a single WBS element; CJ12 changes and CJ13 displays it.Project managerECC + S/4HANA
CN21UserCreate a network; CN22 changes and CN23 displays it.Project plannerECC + S/4HANA
CN24NUserOverall network scheduling: several linked networks at once.Project plannerECC + S/4HANA
CN41NUserProject structure overview: definition, WBS, networks, activities, milestones, components and confirmations in one report.EveryoneECC + S/4HANA
CN43NUserOverview of WBS elements across projects; CN42N lists project definitions and CN53N milestones.Project manager, controllerECC + S/4HANA
CJ40UserOverall cost planning on the WBS; CJ41 displays it.Project controllerS/4HANA: classic planning tables
CJR2UserCost element and activity input planning on the WBS; CJR3 displays it.Project controllerS/4HANA: classic planning tables
CJ9ECPUserEasy Cost Planning for projects: quick cost estimates on WBS elements.Project controllerECC + S/4HANA
CJ42UserRevenue planning on billing elements; CJ43 displays it.Project controllerECC + S/4HANA
CJ30UserOriginal budget; CJ31 displays it.Project controllerECC + S/4HANA
CJ32UserBudget release; CJ33 displays it.Project controllerECC + S/4HANA
CJ34UserBudget transfer between WBS elements or projects.Project controllerECC + S/4HANA
CJ36UserBudget supplement to one or more projects; CJ37 supplements inside one project.Project controllerECC + S/4HANA
CJ35UserBudget return from a project; CJ38 returns inside one project.Project controllerECC + S/4HANA
CJ3AUserChange a budget document; CJ3B displays it.Project controllerECC + S/4HANA
ME21NUserPurchase order with account assignment P (project), Q (project stock) or N (network).BuyerECC + S/4HANA
MIGOUserGoods movements: goods issue 221 to a WBS element or 281 to a network, receipts for project orders.WarehouseECC + S/4HANA
CN25UserConfirm a network activity: hours, remaining work, completion.Project teamECC + S/4HANA
CN27UserCollective confirmation of many activities; CN29 cancels confirmations.SupervisorECC + S/4HANA
CAT2UserEnter time in the Cross-Application Time Sheet.Project teamECC + S/4HANA
CAT5UserTransfer time sheet data from CATS to PS.Supervisor, background jobECC + S/4HANA
CJI3UserActual cost line items for projects.EveryoneS/4HANA: compatibility scope
CJI3NUserActual cost line items, the newer version and the successor of CJI3.EveryoneS/4HANA: successor of CJI3
CJI4UserPlan cost line items.Project controllerECC + S/4HANA
CJI5UserCommitment line items: open purchase requisitions and orders.Project manager, controllerECC + S/4HANA
CJI8UserBudget line items.Project controllerECC + S/4HANA
S_ALR_87013558UserBudget, actual, commitment, remaining plan and assigned for each WBS element.Project manager, controllerECC + S/4HANA
CJE0UserRun a hierarchy report: costs, revenues and budget along the project hierarchy.Project controllerECC + S/4HANA
CNE1UserProgress analysis: calculate percentage of completion and earned value for a project; CNE2 for many.Project controllerECC + S/4HANA
CNE5UserProgress analysis structure overview.Project managerECC + S/4HANA
CNMTUserMilestone trend analysis.Project managerECC + S/4HANA
CN72UserCreate a project version, a snapshot to compare with later.Project managerECC + S/4HANA
DP91UserResource-related billing request for customer projects.Billing clerkECC + S/4HANA
CJ91ConsultantStandard WBS, the template for new projects; CJ92 changes and CJ93 displays it.PS key userECC + S/4HANA
CN01ConsultantStandard network, the template for networks; CN02 changes and CN03 displays it.PS key userECC + S/4HANA
OPSAConsultantProject profile: organization, profiles and WBS settings for new projects.PS consultantECC + S/4HANA
OPSJConsultantProject coding mask: the format of project and WBS numbers.PS consultantECC + S/4HANA
OPSCConsultantNetwork types.PS consultantECC + S/4HANA
OPUUConsultantNetwork profile: defaults such as control keys and cost elements for activities.PS consultantECC + S/4HANA
OPSUConsultantControl keys for network activities.PS consultantECC + S/4HANA
OPSBConsultantPlanning profile for cost planning on WBS elements.PS consultantECC + S/4HANA
OPS9ConsultantBudget profile: overall or annual budget, availability control and its activation.PS consultantECC + S/4HANA
OPI1ConsultantValue categories for the project information system; OPI2 assigns cost elements to them.PS consultantECC + S/4HANA
OITAConsultantInvestment profile: automatic asset under construction and its asset class.PS and FI-AA consultantECC + S/4HANA
OPTTConsultantAccount assignment category and document type for purchase requisitions from networks.PS and MM consultantECC + S/4HANA
OKKPConsultantControlling area settings, where the Projects component must be active.CO consultantECC + S/4HANA
CJBVConsultantActivate availability control for existing projects; CJBW deactivates it.PS consultantECC + S/4HANA
CJBNConsultantReconstruct availability control, after CJBW when settings change.PS consultantECC + S/4HANA
CJENConsultantReconstruct the summarized project data, the project information database.PS consultantECC + S/4HANA
CNMASSConsultantMass change of project objects, with a test run and a log.PS consultantECC + S/4HANA
BS23ConsultantSystem statuses and the business transactions each one allows or forbids.PS consultantECC + S/4HANA
CJ88FI/CO bridgeSettle one project: periodic, full or preliminary settlement.Project controller, asset accountantECC + S/4HANA
CJ8GFI/CO bridgeCollective settlement of projects and networks.Project controllerECC + S/4HANA
CJ44FI/CO bridgeActual overhead for one project; CJ45 for many.Project controllerECC + S/4HANA
CJZ2FI/CO bridgeActual interest calculation for one project; CJZ1 for many.Project controllerECC + S/4HANA
KKA2FI/CO bridgeResults analysis for one WBS element; KKAJ for many.Project controllerECC + S/4HANA, not with UPA
CJICFI/CO bridgeLine-item settlement: assign single AuC line items to final assets.Asset accountantECC + S/4HANA
AW01NFI/CO bridgeAsset Explorer: the AuC and the final assets with their values.Asset accountantECC + S/4HANA
AIBUFI/CO bridgeSettle a stand-alone AuC that no project manages.Asset accountantECC + S/4HANA
KP26FI/CO bridgeActivity prices: the rates confirmations charge to the project.Cost accountantS/4HANA: classic planning tables
CJCFFI/CO bridgeCarry forward project commitments to the new year.Project controllerECC + S/4HANA
CJCOFI/CO bridgeCarry forward unused project budget to the new year.Project controllerECC + S/4HANA
Project Cost OverviewFiori appPlanned and actual costs of a project, its WBS elements, networks and maintenance orders (F6991).Project controllerS/4HANA 2022 FPS1
Project Cost Line ItemsFiori appThe line items behind the project costs, with navigation to journal entries (F6992).Project controllerS/4HANA 2022 FPS1
Project ScheduleFiori appGantt chart of the project structure and dates, the modern planning board.Project plannerS/4HANA 2021
Project Network GraphFiori appNetwork activities and relationships as an interactive graph; finds loops.Project plannerS/4HANA 2020 FPS1
Monitor ProjectsFiori appPlan, actual, commitments and budget of projects in graphics, with variances (F3088).Project controllerS/4HANA
Project Budget ReportFiori appBudget and commitments of projects.Project controllerS/4HANA
Project Financial Controller OverviewFiori appOverview page with cards for project controllers.Project controllerS/4HANA
Project TextFiori appThe renewed PS texts.Project managerS/4HANA 2021 FPS1
Event-Based Revenue Recognition – ProjectsFiori appRevenue situation of each billing element; adjust and revalue.Project controllerS/4HANA
Project Control – Enterprise ProjectsFiori appCreate and control enterprise projects in the cloud editions.Project controllerS/4HANA Cloud
PROJTableProject definitions.ConsultantsECC + S/4HANA
PRPSTableWBS element master data, with the indicators PLAKZ, BELKZ and FAKKZ.ConsultantsECC + S/4HANA
PRHITableWBS hierarchy pointers.ConsultantsECC + S/4HANA
PRTETableScheduling data of WBS elements.ConsultantsECC + S/4HANA
AUFK / AFKOTableNetwork headers, as orders with order category 20.ConsultantsECC + S/4HANA
AFVC / AFVVTableNetwork activities and their dates and quantities.ConsultantsECC + S/4HANA
RESBTableMaterial components of networks (reservations).ConsultantsECC + S/4HANA
MLSTTableMilestones.ConsultantsECC + S/4HANA
AFRUTableConfirmations.ConsultantsECC + S/4HANA
JESTTableStatuses of every object; TJ02T holds the status texts.ConsultantsECC + S/4HANA
BPGE / BPJATableBudget totals, overall and annual.ConsultantsECC + S/4HANA
RPSCOTableProject information database: costs, revenues and finances that hierarchy reports read.ConsultantsECC + S/4HANA
COOITableCommitment line items.ConsultantsECC + S/4HANA
COBRA / COBRBTableSettlement rule and its distribution rules.ConsultantsECC + S/4HANA
EVPOCTablePercentage of completion from progress analysis.ConsultantsECC + S/4HANA
MSPRTableProject stock.ConsultantsECC + S/4HANA
ACDOCA / ACDOCPTableUniversal journal actuals and plan data in SAP S/4HANA.ConsultantsS/4HANA

Standard codes, cross-checked with SAP Help (project period-end closing and standard structures), SAP Learning, SAP KBAs, the SAPSTACK and ERPlingo lists and SAP Community; S/4HANA changes from the SAP blog on the EPPM compatibility scope and SAP Note 2270407 as described by SAP; Fiori app names from SAP Learning and SAP blogs. Projects can hide transactions or rename apps, so check your own system before you write them into a manual.

ECC to S/4HANA

What changed in PS with SAP S/4HANA

The project works the way it did in SAP ECC: same structures, same Project Builder, same settlement. What changed sits around it: planning moving to ACDOCP and SAP Analytics Cloud, reports and screens moving to Fiori, revenue recognized in real time, and a list of old functions that SAP either modernized or left without a successor.

  • The Project Builder

    ECCCJ20N and the Project Planning Board in SAP GUI.

    S/4HANAStill CJ20N on premise and in the private cloud, with the Project Schedule and Project Network Graph apps beside it.

    In SAP S/4HANA Cloud Public Edition the Project Builder app was deprecated with release 2202; enterprise projects there are maintained with the Project Control and Project Planning apps.

    Source: SAP KBA 3130810, Project Builder in the public cloud
  • Cost planning

    ECCCJ40, CJR2 and Easy Cost Planning write the CO totals tables.

    S/4HANAThe classic transactions still work, per SAP Note 2270407, but write the classic tables, not ACDOCP.

    Easy Cost Planning and network costing integrate with ACDOCP from release 2022, and SAP Analytics Cloud is the strategic planning tool. The program that moves classic plans to ACDOCP leaves CJ40 data behind.

    Source: SAP blog, controlling in SAP S/4HANA, part 2 (2020)
  • Project reports

    ECCHierarchy reports such as CJE0 and S_ALR_87013558, line items in CJI3.

    S/4HANAProject Cost Overview and Project Cost Line Items apps, from 2022 FPS1.

    Cost element and summarization reports stay; CJI3 remains in compatibility scope, with CJI3N as its successor.

    Source: SAP blog, compatibility scope for EPPM (2023)
  • Revenue recognition

    ECCResults analysis (KKA2, KKAJ) at period end, then settlement to profitability.

    S/4HANAEvent-based revenue recognition: recognized revenue posted at each event, from release 1610.

    Results analysis is still there but not supported with Universal Parallel Accounting. In the public cloud, customer projects need no settlement: the market segment is on every line item.

    Source: SAPinsider, real-time revenue recognition
  • Capitalizing small projects

    ECCPeriodic summary settlement from the WBS element to the AuC.

    S/4HANAEvent-based settlement: costs of small investment projects post straight to the AuC.

    Line items stay visible on the AuC; the full settlement to the final assets still uses settlement rules.

    Source: SAP Learning, small investment projects
  • The Gantt chart

    ECCProject Planning Board (CJ2B) and network graphic.

    S/4HANAProject Schedule app from 2021, Project Network Graph from 2020 FPS1.

    The planning board itself is still there; the apps add a browser-based Gantt chart and an interactive network graph that finds loops.

    Source: SAP Learning, checking the project schedule
  • What has no successor

    ECCProduction resources and tools, hierarchy graphics, network progress, the Forecast Workbench, CJCD change documents.

    S/4HANAKept in compatibility scope, most without a planned successor.

    Change documents move to CN60, consistency checks to validations, PS archiving transactions to central archiving. SAP closed the modernization of the remaining PS items with release 2023.

    Source: SAP blog, compatibility scope for EPPM (2023)
  • PS texts and claims

    ECCPS texts and Claim Management in SAP GUI.

    S/4HANAThe Project Text app (2021 FPS1), and an API plus the Project Claim Overview app (2022).

    Both had been compatibility scope items; SAP modernized them instead of dropping them.

    Source: SAP blog, compatibility scope for EPPM (2023)
  • PS Cash Management

    ECCIts own data, filled by separate transfers.

    S/4HANAReads from the universal journal, from release 2023.

    One of the project financial planning and control functions SAP rebuilt on the universal journal.

    Source: SAP blog, compatibility scope for EPPM (2023)
  • Commercial Project Management

    ECCAn add-on.

    S/4HANAPart of the SAP S/4HANA core from release 1709.

    CPM sits on top of PS projects: business function OPS_PS_CI_1 is a prerequisite for working with them.

    Source: SAP blog, CPM in SAP S/4HANA (2018)
  • Enterprise projects in the cloud

    ECCClassic PS projects only.

    S/4HANASAP S/4HANA Cloud runs enterprise projects with the Project Control, Project Planning and Project Brief apps.

    From 1808 a budget availability control profile on the project checks postings against the budget and warns or blocks, as in classic PS.

    Source: SAP blog, SAP S/4HANA Cloud 1808 for EPPM
  • Planned costs from portfolios

    ECCPlanned costs of a portfolio item stayed in PPM.

    S/4HANATransferred to the linked PS project into ACDOCP, from 2022 FPS1.

    Plan-versus-actual for portfolio-driven projects can be reported from the same plan table as the rest of finance.

    Source: SAP blog, compatibility scope for EPPM (2023)

Brazil

Capital projects in Brazil: three tax clocks

Elsewhere, the moment an asset under construction becomes a fixed asset is an accounting event. In Brazil it is also a tax moment: ICMS, PIS/COFINS and the new IBS and CBS on the same machine follow different clocks, and the AuC settlement is where tax and project teams meet.

  • ICMS · CIAP

    48 months, from when the asset works

    ICMS on goods for the fixed assets is credited at 1/48 a month for 48 months, in proportion to taxed outputs, and controlled in the CIAP, Block G of the EFD ICMS/IPI. For assets that enter service later, São Paulo’s tax authority has answered that the first fraction starts when the asset goes into operation, so parts bought for an asset under construction wait.

    Sources: SEFAZ-SP, Resposta à Consulta 9135/2016; Planning, CIAP
  • PIS/COFINS

    On depreciation, as a rule

    Under the non-cumulative regime, the general rule calculates the PIS and COFINS credit on the depreciation of the asset. The credit follows the final asset’s depreciation, which only starts once the project has capitalized it.

    Source: Grupo CPCON, IBS and CBS credit on fixed assets
  • IBS · CBS

    Full and immediate credit

    Article 108 of Complementary Law 214/2025 grants full and immediate IBS and CBS credit on capital goods, subject to proof that the tax on the purchase was paid. ICMS ends on 31 December 2032; CIAP credits already running keep their 1/48 schedule until they finish.

    Sources: LC 214/2025, art. 108; Reforma Tributária, CIAP and the reform

Documented, but little known

18 tips for users and consultants

Each tip comes from SAP Help, SAP Learning, an SAP knowledge base article, an SAP blog or SAP Community, linked under the tip.

Audience
  • 01Users

    Ask the status what it allows

    In the Project Builder, the status button on a WBS element opens a Business processes tab: allowed transactions in green, forbidden ones in red. It answers most “why can’t I” questions in seconds.

    • CJ20N
    Source: SAP Community, the Business processes tab
  • 02Users

    Open the whole project in one report

    CN41N shows project definition, WBS elements, networks, activities, milestones, components and confirmations in one tree, and from the structure information system you can confirm activities or start a mass change.

    • CN41N
    Source: SAP Learning, activity confirmation and CATS
  • 03Users

    Your purchase order already used the budget

    Availability control counts open purchase requisitions and orders as assigned, not only invoices. CJI5 lists those commitments, and closing old ones frees budget.

    • CJI5
    • CJ31
    Source: SAP Help, tolerance limits
  • 04Users

    Hours in CATS are not on the project yet

    Time sheet entries reach the network only after the CAT5 transfer; records that cannot post land in an error pool to be processed in PS.

    • CAT2
    • CAT5
    Source: SAP Community, CATS transfer and the error pool
  • 05Users

    Cancel many confirmations at once

    Collective confirmation is CN27, but wrong confirmations are cancelled with CN29, not inside CN27.

    • CN27
    • CN29
    Source: SAP KBA 3700110, CN27 and CN29
  • 06Users

    Watch milestones drift

    Milestone trend analysis compares milestone dates across project versions to show whether the project is on, ahead of or behind schedule; versions come from CN72 or are created by status.

    • CNMT
    • CN72
    Source: SAP Learning, project versions and milestone trend analysis
  • 07Consultants

    BS23 shows every status rule

    BS23 lists each system status and the business transactions it allows or forbids: the rules behind the Business processes tab.

    • BS23
    Source: SAP Community, TECO and BS23
  • 08Consultants

    Changed tolerance limits? Deactivate first

    After changing availability control settings, deactivate it (CJBW) and then reconstruct it (CJBN). As quoted from SAP Note 922295, reconstructing alone is not enough.

    • CJBW
    • CJBN
    Source: SAP Community, deactivate before reconstructing (Note 922295)
  • 09Consultants

    The coding mask is a one-way door

    You can add to a project coding mask later, but you cannot take anything away once WBS elements use it. Design it before the first project goes live.

    • OPSJ
    Source: SAP Learning, customizing WBS
  • 10Consultants

    One AuC per project, not per element

    An investment profile defaulted in the project profile lands on every WBS element and creates an AuC for each at release. Put it only on the element that should be the investment measure.

    • OITA
    • OPSA
    Source: SAP KBA 3463536, an AuC for every WBS element
  • 11Consultants

    LKD does not stop MRP

    A locked WBS element refuses a manual purchase requisition with BS013, but MRP still creates procurement proposals for it.

    • MD04
    • ME51N
    Source: SAP KBA 2797833, MRP and status LKD
  • 12Consultants

    Test mass changes first

    Mass changes across projects can run as a test with a log, and many cannot be undone. Run the test, read the log, then change.

    • CNMASS
    Source: SAP Learning, mass changes
  • 13FI/CO

    BP603 is not only for purchase orders

    SAP has knowledge base articles for “budget exceeded” on service entry sheets (ML81N), on time sheet hours and even in the depreciation run (AFAB). Any transaction that assigns cost can hit availability control.

    • ML81N
    • AFAB
    Source: SAP KBA 3730654, BP603 in ML81N
  • 14FI/CO

    Budget transfers are checked line by line

    In CJ34 availability control evaluates each transfer line on its own, not the sum, so one line can fail although the whole transfer fits.

    • CJ34
    Source: SAP KBA 3683535, BP603 in CJ34
  • 15FI/CO

    Reports and availability control can disagree

    The assigned value availability control works with is calculated differently from PS reporting, so S_ALR_87013558 and the availability control overview may not match. SAP’s central KBA lists the differences.

    • S_ALR_87013558
    • CJBN
    Source: SAP KBA 3275655, budget and availability control
  • 16FI/CO

    CJ40 plans don’t move to ACDOCP

    The program that transfers classic plan data to ACDOCP leaves CJ40 overall planning behind, so Fiori plan-versus-actual reports can show no plan for those projects.

    • CJ40
    Source: SAP KBA 3525131, CJ40 plan data and ACDOCP
  • 17FI/CO

    Create the final assets before the full settlement

    The AuC settles to final assets only after they exist and are entered in the settlement rule of the WBS element; otherwise CJ88 reports that the AuC is not completely credited.

    • CJ88
    • AW01N
    Source: SAP Community, create the completed asset first
  • 18FI/CO

    Results analysis and UPA don’t mix

    Universal Parallel Accounting does not support results analysis, so customer projects in a UPA system need event-based revenue recognition.

    • KKA2
    Source: SAP blog, EBRR with Universal Parallel Accounting (2022)

Myths

Things people get wrong about PS

  • MythCosts are posted to the project.

    FactCosts are posted to WBS elements, networks and activities. The project definition is only the frame and is not an account assignment object.

  • MythIn CRTD nothing can happen.

    FactIn CRTD you can plan, budget and even create purchase requisitions and orders. Only actual postings wait for REL.

  • MythAvailability control checks the actual costs.

    FactIt checks the assigned value: actual costs plus open commitments such as purchase requisitions and orders. A purchase order can be blocked before a cent is spent.

  • MythThe budget is the plan.

    FactThe plan is an estimate; the budget is approved money, entered in CJ30 and often proposed from the plan. Availability control checks the budget, never the plan.

  • MythTECO closes the project.

    FactTECO says the work is done but costs are still expected, so invoices for existing orders still post. Only CLSD blocks actual postings.

  • MythA network is just a Gantt chart.

    FactA network is an order, in the same tables as production orders, with order category 20. It carries costs, components, purchase requisitions and confirmations.

  • MythYou can post straight to the AuC.

    FactThe AuC of an investment measure cannot be posted directly: costs go to the WBS element and reach the AuC by settlement, or with event-based settlement through the cost posting itself.

  • MythCJR2 plans show up in the new SAP S/4HANA reports.

    FactClassic planning transactions such as CJ40 and CJR2 still write the classic tables, not ACDOCP, which the newer Fiori reports read.

Evolution

From R/2’s project costing to Fiori apps

Projects were part of SAP’s cost accounting long before they had screens of their own, and their field names still carry the German of those years. Gold dots mark the SAP S/4HANA era.

  1. 1979SAP R/2SAP R/2 launches. Among its modules is RK-P, cost accounting for projects.
  2. 1992SAP R/3SAP R/3 launches, the line in which the Project System, PS, grows into its own component.
  3. 2003cProjectscProjects arrives beside PS for phase-and-gate project management; it later becomes SAP Portfolio and Project Management.
  4. 2015SAP S/4HANASAP S/4HANA launches. PS stays, with its structures and transactions.
  5. 2016Release 1610A time confirmation on a customer project can post revenue recognition at once: event-based revenue recognition.
  6. 2017Release 1709Commercial Project Management becomes part of the SAP S/4HANA core.
  7. 2020Release 2020 FPS1The Project Network Graph app.
  8. 2021Release 2021The Project Schedule app, a browser Gantt chart beside the planning board, and renewed PS texts.
  9. 2022Releases 2202 and 2022 FPS1The public cloud deprecates the Project Builder app (release 2202); on premise, 2022 FPS1 brings the Project Cost Overview and Line Items apps.
  10. 2023Release 2023SAP closes its modernization of the PS compatibility scope items.

The WBS fields behind the screens

PRPSField
POSIDWBS element, as you type it
PSPNRWBS element, internal number
POST1Short description
PLAKZPlanning element
BELKZAccount assignment element
FAKKZBilling element
PRCTRProfit center
FKSTLResponsible cost center
OBJNRObject number: the key to statuses, budgets and settlement rules

PSP is the German Projektstrukturplan, the WBS. Sources: SAPSTACK and sapdatasheet, table PRPS; SAP blog, PS tables and their links.

Where a project lives

TableHolds
PROJProject definitions
PRPSWBS elements
PRHIWBS hierarchy
AFKONetwork headers
AFVCNetwork activities
MLSTMilestones
BPGEBudget, overall values
RPSCOProject information database
COBRBSettlement distribution rules

Sources: SAP Community, PS tables; SAP blog, PS tables and their links; SAPinsider, RPSCO.

Sources: Wikipedia (SAP R/2, SAP R/3); our SAP cProjects page and its sources; SAPinsider, real-time revenue recognition; SAP blogs on CPM in SAP S/4HANA, the EPPM compatibility scope and the Project Schedule app; SAP KBA 3130810.

The questions people ask most

What is the difference between a WBS element and a network?

The WBS element structures the work and the money: it carries plans, budgets, actual costs and the settlement rule. The network structures the time: activities with durations and relationships that schedule the work, plan internal hours, buy materials and services and collect confirmations. The network’s costs are settled to the WBS element it belongs to.

Why can’t I post to my WBS element?

Check four things. The system status: CRTD allows planning but no actual postings, CLSD blocks them, LKD or AALK lock them. The account assignment indicator: only account assignment elements take postings. Availability control: budget exceeded, message BP603. And the user status, which can forbid transactions on top of the system status. The status button in the Project Builder shows what is allowed.

What do CRTD, REL, TECO and CLSD mean?

Created: structure and planning, no actual postings. Released: actual costs and revenues post. Technically completed: the work is done but costs are still expected, so invoices for existing orders still post; it can be revoked. Closed: no more actual postings and the AuC is deactivated; it can be revoked back to TECO.

What is the difference between plan, budget and release?

The plan is the cost estimate, entered top-down or calculated from the network. The budget is the approved amount, entered as an original budget in CJ30 and changed by supplements, returns and transfers. A budget release, CJ32, makes part of the budget available to spend, when the budget profile asks for it.

What is availability control?

A check of the assigned value, actual costs plus open commitments, against the budget or the release of a WBS element. Tolerance limits per activity group decide when it warns, warns with a mail to the person responsible, or rejects the document with an error.

Why did my purchase order fail with “budget exceeded”?

Because the order, added to what was already assigned, went past the error limit: message BP603. Below the budget the message is BP613, budget almost exhausted. Ask for a supplement or a transfer, reduce the order, or close commitments that will never be invoiced.

Why does S_ALR_87013558 show a different available budget than availability control?

The assigned value availability control works with is calculated differently from PS reporting. SAP’s central KBA 3275655 explains the differences; reconstructing the project information database (CJEN) and availability control (CJBN) aligns old data.

How does a capital project become a fixed asset?

The investment profile on the WBS element creates an asset under construction when the element is released, and the first settlement creates the rule to it. Each month CJ88 settles the costs to the AuC. When the project is complete, you create the final assets, enter them in the settlement rule and run a full settlement, which credits the AuC and debits the assets.

What is the difference between results analysis and event-based revenue recognition?

Results analysis (KKA2, KKAJ) runs at period end and calculates the revenue to recognize, work in process and reserves into separate tables, which settlement then passes on. Event-based revenue recognition, in SAP S/4HANA, posts recognized revenue in the universal journal at each cost or billing event, so margins are visible in real time. Results analysis is not supported with Universal Parallel Accounting.

What is the difference between a supplement, a return and a transfer?

A supplement adds money (CJ36 to one or more projects from outside, CJ37 inside one project), a return gives money back (CJ35 out of the project, CJ38 inside it) and a transfer moves it from one WBS element or project to another (CJ34). The original budget stays visible, so the budget history can be traced.

Account assignment P, Q or N: which one?

P posts the cost to the WBS element directly, like a non-stock purchase. Q keeps the material in project stock, quantity and value per WBS element, and the cost reaches the project at the goods issue. N assigns the cost to a network activity.

Can I still use CJ40 and CJR2 in SAP S/4HANA?

Yes, on premise and in the private cloud, as SAP Note 2270407 describes. They write the classic tables, though, not ACDOCP, which the newer Fiori reports and SAP Analytics Cloud work with.

PS, PPM (cProjects) or CPM: which one does what?

PS is the execution and financial backbone: WBS elements, networks, costs, budgets and settlement. SAP Portfolio and Project Management, the former cProjects, manages phases, approvals and portfolios and can transfer its projects to PS for the accounting. Commercial Project Management adds commercial planning on top of PS projects, which it needs underneath.

What has to run at year end?

Besides the usual settlement and closing, open commitments are carried forward with CJCF and unused annual budget with CJCO, so purchase orders and budgets continue in the new fiscal year.

References